Big Rigging Setup in Port of Antwerp

Posted in: Case Studies
We were given the chance to provide lifting equipment for a hose tower in the Port of Antwerp. We worked with several companies to provide a proper lifting solution. The hose tower itself weighs around 315T and our equipment itself around 40T. The hosetower is hanging below: - 2x modular lifting beam of 400T on 14m - 2x modular lifting beam of 250T on 15m - 2x modular lifting beam of 110T at 9.5m - 2x modular lifting beam of 110T at 9m - 8x modular lifting beam of 50T on 5m - 48 slings - 80 shackles All of our spreader beams are from our trusted partner Modulift.

See the full video here!

21 July 2020
46 view(s)
Did you like this post?
0
0